Cost reporting
Cost reporting is a process used to inform a client (or other party) about the magnitude of a construction project’s predicted, or actual cost. This can be expressed either in absolute terms or as a variance compared to the project budget.
Cost reports are typically prepared by a cost consultant (such as a quantity surveyor) and updated regularly (perhaps monthly), to keep the client informed and to help them and the project team control costs.
Typically, cost reports will evolve through the life of the project, developing in detail and accuracy as more information becomes available about the nature of the design, and then actual prices are provided by specialist contractors, contractors and suppliers, and actual costs incurred.
A cost report will generally include all the costs incurred by the date of the report, where they are known, a forecast of the costs likely to be incurred during the rest of the project, in so far as these can be foreseen and estimated, and risk allowances for the possibility of unforeseeable costs. Contingencies to cover these risks are often expressed in terms of percentages. The percentages applied are at their greatest in the early stages of the project when there are the greatest number of possible risks, but they can then be reduced as better particulars about the project become available and some risks have passed or been overcome.
It is important to be clear what costs will be included in cost reports. For example, the client may have costs that, whilst they are directly related to the project, they would prefer to account for them themselves. This might include; land acquisition costs, specialist plant or equipment, furniture, construction contracts outside of the main contract and so on.
In the absence of a single, standard type of cost report format, or specific formatting requirements by the client, most cost consultants will develop their own format for cost reports.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.